Update June 23 Trail Resurfacing
- Posted On June 23, 2017
- By Chris Ziegler
- In Featured
- 1
*IMPORTANT NOTICE*
“Tentative” Butler-Freeport Trail “RESURFACING” Schedule
(per Brad Jeannerat with JC Lee Construction/Ken Howard with Bankson Engineers as of 6/23/17)
*The Butler-Freeport Trail will be “OPEN” Friday, 6/23/17 through Monday, 6/26/17*
JC Lee Construction will be working in the area of the Derailleur Bike Shop on Tuesday, 6/27/17 to finish up rolling/fine tuning and reinstalling the gates down to the Marwood Road Trailhead. If all goes well (no breakdowns or rainstorms) they will complete that section of the trail on Tuesday, 6/27/17.
The “TRAIL CLOSED” signs will be posted at Sheetz Drive, Great Belt Road, Jones Road, Keasey Road and Marwood Road until completion of Section 3.
————————————————————————————–
JC Lee Construction will be working Wednesday, 6/28/17 in section 1, which is the Laneville area in Freeport. At that time, the Butler-Freeport Trail will be “COMPLETELY CLOSED TO ALL PEDESTRIAN/BIKE TRAFFIC” from Laneville in Freeport to Monroe Road (MABT Treatment Plant). JC Lee Construction will be “Resurfacing and Installing Drainage Pipes” in that area of the Trail.
The “TRAIL CLOSED” signs will be posted at Laneville in Freeport and Monroe Road (MABT Treatment Plant) until completion of Section 1
**THIS SECTION OF THE BUTLER-FREEPORT TRAIL WILL BE COMPLETELY CLOSED TO ALL PEDESTRIAN/BIKE TRAFFIC**
***FOR YOUR SAFETY PLEASE “DO NOT BIKE OR WALK” ON THE TRAIL DURING THE TRAIL RESURFACING PROJECT***
Construction update 6-15-17
- Posted On June 15, 2017
- By Chris Ziegler
- In Featured
- 0
Trail is open. JC Lee is done resurfacing from Herman to Marwood, they still have to re-installing the gate and go through final inspection next Friday. Please do not use Sheetz Dr Trailhead as the still need to hauling equipment and material out. moving in to Laneville Monday. Starting then and for about a month Laneville to under the 28 bridge will be closed during the day. Open nights and weekends. Please mind the signs, this will go faster and be safer for everyone if folks stay away during the day.
Update 6-11-17
- Posted On June 11, 2017
- By Chris Ziegler
- In Featured
- 0
TRAIL CLOSURE. Sheetz Drive to Marwood Road will be closed Monday-Thursday during the day this week. Please respect the closure, the contractor can work much more effectively without worring about walkers and bikers. Short term pain, long term gain. Enjoy
Update 6-5 Resurfacing project
- Posted On June 05, 2017
- By Chris Ziegler
- In Featured
- 0
*IMPORTANT NOTICE*
“Tentative” Butler-Freeport Trail Repaving Schedule
(per Brad Jeannerat with JC Lee Construction as of 6/2/17)
JC Lee Construction will be closing the Butler-Freeport Trail from Sheetz Drive to Marwood Road on Monday, June 5th, 2017 – Friday, June 9th, 2017 (weather permitting)
for the trail repaving project.
The “TRAIL CLOSED” signs will be posted at Sheetz Drive, Great Belt Road,
Jones Road, Keasey Road and Marwood Road.
**FOR YOUR SAFETY PLEASE “DO NOT BIKE OR WALK” ON THE TRAIL DURING THE TRAIL REPAVING PROJECT**
Update on construction end of day June 2nd
- Posted On June 02, 2017
- By Chris Ziegler
- In Featured
- 0
Trail is open but please be mindful when riding on the new surface.
Monday, June 5th trail will be closed from Sheetz to Great Belt, parking areas will both be closed as well. Enjoy.